ISO-NE Advanced Solar Inverter Functionality
ISO-NE
UL 1741 SA

 

This article is a follow-up to a previous article discussing UL 1741 & Rule 21: Advanced Inverter Tests. We suggest you start with that article first.

Seemingly discontent to be left out of the advanced inverter functionality game, ISO New England (ISO-NE) recently announced new requirements for interconnected PV inverters in Massachusetts. Similar to California’s Rule 21, the new ISO-NE settings requirements are designed to maintain grid stability and resilience during both normal and abnormal operating conditions in the presence of a large volume of interconnected dynamic PV systems.

To achieve this mandate ISO-NE has promulgated a set of inverter ride-through requirements to be manually adjusted on UL 1741 SA  inverters that specify voltage and frequency trip settings and ride-through capability described in the ISO-NE Inverter Source Requirement Document. Implementation of these setting requirements vary by system size:

 

  • < 100kW: All inverter-based solar PV projects 100kW or less with applications submitted on or after June 1, 2018 are subject to ISO-NE Ride-through Requirements.
  • > 100kW: All inverter-based solar PV projects greater than 100KW with applications submitted on or after March 1, 2018 are subject to ISO-NE Ride-through Requirements.
    • Inverter-based solar PV projects with applications submitted prior to the above dates are encouraged to comply with ISO-NE Ride-through Requirements with the approval of the interconnecting utility.

 

Don’t fret. ISO-NE is actively engaging inverter manufacturers to ships units with a pre-programmed NE Regional Setting Group, that when selected, defaults to the required setting described in the ISO-NE Inverter Source Requirement Document.

What does this mean for your next PV project in the Commonwealth? First, be sure you are purchasing and installing UL 1741 SA compliant inverters. Below is a short list of compliant manufacturers. Secondly, begin to become comfortable with the ins-and-outs of the new setting requirements and how they are made. It may be several months until a default setting is available

 

 

Work with your Greentech Renewables account manager to ensure your next PV project in Massachusetts is in compliance.

For additional readings, please see below:

  1.  2018 Regional Electricty Outlook, ISO New England, 2018